414 guides across 21 subjects
Every figure traced to a named source
Prices in Ugandan shillings, per acre and per animal

Farm Reservoir Construction

Drip irrigation tape running along a crop row

Farm reservoir construction succeeds or fails on the soil, and you can test the soil for nothing before you spend a shilling on excavation. A dug reservoir holds water only if the ground around and beneath it will not let it through, which rules out sandy sites outright. Everything else, siting, shape, lining, silt and safety, follows from what the auger brings up. Start there, not with a quote for a digger.

This page is about excavated storage: a hole in the ground holding hundreds of cubic metres, filled from run off or pumped in, drawn on through a dry season. Manufactured storage, meaning tanks bought or built as vessels holding thousands of litres, is a different purchase with a different failure list and sits on farm water storage tanks. The two are often confused in quotes and they should not be.

Test the Soil Before You Cost the Digging on a Farm Reservoir

Soil is graded by the proportions of three particle sizes, and FAO's small earth dams manual gives the cut offs it works to: clay below 0.002 millimetres, silt between 0.002 and 0.05, sand from 0.05 to 2.00. A soil above 55 per cent clay counts as a clay; between 33 and 55 per cent clay with up to 65 per cent sand is a sandy clay; between 20 and 30 per cent clay with up to 80 per cent sand and loam is a sandy clay loam.

The manual's verdict on which of these you can build with is short. Sands and clays, and combinations of them, are the suitable materials. Silty soils are unsuitable because of their instability when wet, and it says they should not be included in any of the earthworks at all. It also notes that the lower the clay content, down to an arbitrary minimum as low as 3 to 5 per cent, the more compaction and care the work needs, which is the polite way of saying that a marginal soil multiplies your labour rather than ruling you out.

Why a reservoir in sandy ground fails is a matter of infiltration rate, and FAO's water harvesting manual puts comparative figures on it: about 50 millimetres an hour through sandy soil, 25 through sandy loam, 12.5 through loam and 7.5 through clay loam. Those are rates for water entering soil, not for a reservoir floor under pressure, and under several metres of head the movement is faster still. A sandy site does not lose a little water slowly. It empties.

Three tests FAO describes that cost nothing but your own time, done before any machine is hired.
Auger a grid. Hand auger holes across the proposed floor and the proposed embankment line, to about three metres, so you know what the profile does with depth rather than at the surface. Then open a trial pit or two in the promising spots to see the profile with your own eyes. The commonest expensive surprise is good clay over sand.
Roll a ball, drop it from your waist. Take a small sample, dampen it without soaking it, and work it in your hand. A better quality clay rolls into a thin strip without breaking up, forms a ball that can be dropped onto a flat surface from waist height without cracking unduly, and shows a shiny smooth face when it is cut. That is FAO's own field test and it is the one to learn.
Tell silt from clay while it is wet. Dry, they look and feel alike, which is how silt gets built into embankments. Wet, clay is sticky and plastic while silt feels silky and smooth and tends to disperse. Get this one wrong and you build a wall that slumps.
Fill the auger holes and watch. Fill holes or small pits with water, taking care not to compact the soil inside them, and compare how fast the level falls across the site. FAO describes this as the simplest indication of permeability and relative clay content, and it is the test that answers your real question directly.

One warning from the same manual that catches people out years later. When you take clay from a borrow area, do not strip the impervious layer out completely, because exposing the more permeable material beneath can cause seepage in later years, especially once several metres of water is pressing on it.

Siting a Farm Reservoir: Catchment, Slope and What Feeds It

A reservoir is only as good as what fills it, so the site has to answer two questions at once: will water arrive, and will it stay.

On arrival, the useful discipline from FAO's dam manual is to link the volume you plan to draw to the yield of the catchment in a dry year rather than an average one, because an average year reservoir is empty in the years you most need it. Take the lower figure. If the reservoir is filled by pumping rather than by run off, the same logic applies to the source: size against what the stream or the well gives in February, not in April.

On keeping it, the site wants a natural hollow or a valley head where the ground already does part of the work, firm foundation material, and clay within reach for the embankment and any cutoff. FAO also makes the economic point that building the embankment out of material excavated from the reservoir area gives you a little more storage and costs less than hauling fill, so a site where both can be done in one operation is worth a good deal.

Two things to avoid. A site whose catchment is eroding, because everything that leaves that catchment ends up in your reservoir; the silt section below deals with what that costs. And a site so close to a watercourse that the works amount to damming or diverting it, which changes the permitting position entirely. Taking surface water with a motorised pump, or diverting or impounding more than 400 cubic metres a day, needs a surface water abstraction permit under the Water Act, and separate construction permits apply to works that impound, dam, divert or convey surface water. Confirm what applies to your specific site with the Ministry of Water and Environment or your district water office before you dig, because the requirement attaches to the works as much as to the volume. The permit framework is set out alongside the groundwater rules on boreholes for agricultural irrigation.

Sizing an Excavated Reservoir Against Dry Season Irrigation Demand

Now the volume. Build it up in four steps and do not skip the last two, because they are where farm reservoirs are quietly undersized.

Step one, the crop. FAO's irrigation water needs training material gives reference grass demand of 5 to 6 millimetres a day in a sub humid climate at a mean temperature between 15 and 25 degrees, and 3 to 4 in a humid climate at the same band. Uganda's national mean sits near 23 degrees, so 3 to 6 millimetres a day is the working bracket and your district decides where in it you fall.

Step two, the area and the days. One acre is 4,047 square metres, so a millimetre across it is about 4,047 litres. At four millimetres a day that is 16.2 cubic metres, and across a ninety day dry season it is about 1,458 cubic metres. At three millimetres the same acre and season wants roughly 1,089 cubic metres; at six, about 2,187.

Step three, add evaporation. Step four, add seepage. Both are treated in their own sections below because both are larger than farmers expect, and together they commonly add a quarter to the volume you have to dig.

Look at what that means. A single acre of dry season vegetables wants a reservoir in the region of 1,500 cubic metres before losses. That is a hole roughly thirty metres by twenty five at two metres of average depth, plus the batter on the sides, plus the embankment. It is a serious earth moving job, and it explains something you can see across Uganda: most farm reservoirs serve livestock and a fraction of an acre, not a field, because the field sized version is a construction project rather than a purchase. FAO notes that embankment dams up to fifteen metres high can be built on suitable sites with relatively unsophisticated procedures, and that farm tractors fitted with dam scoops, scrapers and rollers are usually adequate, so the work is within reach. It is the scale that surprises people, not the difficulty.

Shape Decides Your Evaporation Loss on a Farm Reservoir

An open water body loses water to the air continuously, and in East Africa the rate is high enough to change your design. The best measured figure in the region comes from Lake Victoria, where a water balance study puts mean annual evaporation from the lake surface at 1,521 millimetres a year, consistent with earlier published estimates of 1,500, 1,551 and 1,595, and against higher estimates of 1,743 and 1,784 from other methods. The spread across the literature is about 200 millimetres a year, which is small next to the spread in rainfall estimates.

Hold that figure next to Uganda's rainfall and the scale of the problem is plain. The World Bank's climate data puts Uganda's national annual rainfall at 1,283 millimetres on the CRU dataset and 1,577 on the ERA5 dataset. In other words, an open water surface in this region loses roughly as much depth to the air in a year as the sky delivers. FAO's dam manual gives the general range as 0.3 to 2.5 metres a year from temperate to arid climates, and records that evaporation from dams in South Africa has been estimated at 25 to 30 per cent of the water stored each year.

Take the Lake Victoria rate as an order of magnitude and apply it to a ninety day dry season. It works out at about 375 millimetres of depth lost, whatever the reservoir's size. Now hold the stored volume constant at 1,500 cubic metres and change only the shape.

Surface Depth Loss in 90 days
1,000 sq m 1.5 m 375 cu m, 25%
750 sq m 2.0 m 281 cu m, 19%
500 sq m 3.0 m 188 cu m, 13%
375 sq m 4.0 m 141 cu m, 9%

The same water, dug four ways, loses between a tenth and a quarter of itself to the air over one dry season. FAO states the principle directly: a narrow deep reservoir has a much smaller evaporation loss than a broad shallow one. The arithmetic above is what that sentence is worth on a farm, and it is the strongest argument for digging down rather than out that anyone will give you. Note also that the deep version corroborates FAO's South African figure from a completely different direction, since the shallow case lands squarely inside that 25 to 30 per cent band.

Two practical qualifications, stated because they matter. The 1,521 millimetre figure is for a very large lake with its own microclimate, not for a small farm pond in Nakasongola or Kabale, and no Ugandan measurement of small pond evaporation was available to substitute. So treat it as an order of magnitude that the shape comparison rests on, rather than as your pond's rate. And whatever the rate turns out to be locally, the ratio between the four rows above does not change, because it depends only on surface area.

Seepage and Why Every Farm Reservoir Leaks

FAO's position is unambiguous and worth quoting in substance: seepage will always occur with an earth dam, and how much depends on the site soils, the embankment itself and the depth of the water. There is no such thing as a sealed excavated reservoir. The design question is how much leakage you accept, not whether you have any.

Three measures reduce it, in ascending order of cost. Compaction is the first and the cheapest, and it is the one most often skipped on farm work. FAO is emphatic that compaction is part of the construction process whatever the size of the embankment, that it should be done in layers, and that it is worth paying more for the equipment because the cost comes back in a better and safer structure. Hand tamping with poles of 100 to 150 millimetres diameter works; so do water filled tractor tyres run in a staggered track across the fill.

Second, a cutoff trench. A trench cut through the permeable material under the embankment and backfilled with well compacted clay reduces seepage and improves stability at the same time. FAO says it should ideally reach solid rock, and gives the working method for small hand laid cores: material placed in layers 50 to 75 millimetres thick and a minimum of one metre wide, every layer well compacted, with each section keyed and bonded to the next so the trench and core behave as one piece.

Third, a liner, which is the next section. Before reaching for one, be clear about what is leaking. Seepage through the floor of a clay lined bowl is a different problem from seepage under or through an embankment, and a plastic sheet on the floor does nothing about the second.

One design detail that changes how much of your water you can actually use. FAO calls the part of a reservoir that cannot be drained by the outlet or reached by the pump its dead storage. A flooded suction taken through the wall leaves very little dead storage; a pump sitting on the bank or on the embankment never brings the level to zero. Decide that before you dig, because retrofitting a through wall outlet to a full reservoir is not a small job. FAO also warns that it is not always wise to drain a reservoir completely, particularly where clays that crack on drying were used in the embankment, core or floor.

Lining Options for a Farm Reservoir in Ugandan Soils

Three families, and the honest ranking in this region is not the one most quotes assume.

Compacted clay. The default and, where good clay is available on site, usually the best. It is cheap, repairable, it does not degrade in sunlight, and nothing burrows through it and ruins it. FAO reserves the best clay for the core and the cutoff and insists it is well compacted. Its weakness is clays that crack on drying: the manual says to avoid them in the core, and if they must be used, to compact them carefully and place them low in the structure where they will not dry out, or cover them with a gravel layer or with topsoil and grass. The water harvesting manual names the family to watch, montmorillonite clays, especially vertisols or black cotton soils, and adds that very sandy soils and soils with very poor structure form erodible bunds.

Heavy duty plastic sheeting. Here is the finding that most pages on this subject leave out. FAO records that artificial impermeable materials such as heavy duty plastic sheeting have been used successfully in many parts of the world as an alternative to clay cores, and then states plainly that in the tropics such materials have been found to attract termites and rodents, have been burrowed into by animals, and have not resisted settlement of the embankment after construction. That is three distinct failure modes, all of them live in Uganda. A liner is not the safe default here that it is in a temperate country. If you use one, protect it above and below, expect to inspect it, and do not treat it as a substitute for compaction.

Termite mound material. Widely used because of its high clay content, and FAO says it is losing favour, for reasons worth knowing before somebody recommends it to you: undesirable organic and mineral constituents, variability within a small area so that two loads are not the same material, and a subsequent attraction to termites and their predators even after being treated with insecticide or mixed with diesel. Where nothing else is within economic reach the manual allows it, but says it must be analysed if possible, well killed before excavation, and treated during installation. It also cautions against insecticides that could contaminate the water through seepage, which on a reservoir you will irrigate food crops from is not a small consideration.

One more protective layer belongs here rather than under lining. Wave action eats an unprotected upstream face. Stone pitching laid properly is an inexpensive and effective protection where stone is available locally, and FAO notes it should not be used on the ends of embankments and abutments or along the sides of a spillway, because those areas are extremely sensitive to erosion and want concrete or gabions instead.

Silting and the Desilting Burden on Farm Reservoirs

Every reservoir fills with soil, and this is the cost that nobody puts in the original quote. The uncomfortable part is what FAO says about fixing it: where a reservoir is severely silted, it is not normally economic to excavate it, because moving and safely dumping huge quantities of wet silt is difficult. The manual's preferred remedy is to raise the dam once the sediment inflow has been reduced, which adds storage for a relatively small increase in earthworks.

Read that carefully, because it inverts the usual advice. Desilting is not the plan. Reducing the silt at source is the plan, and raising the wall is the fallback. Silt traps upstream do work, but FAO describes them as stop gap measures, usually temporary, often expensive, and needing regular desilting themselves.

Reducing sediment inflow at source, which is the only durable answer.
Establish cover before you build. FAO suggests conserving the catchment before works commence so vegetative cover is well established by the time the reservoir exists. That is a season of lead time and it is free.
Cultivate on the contour. Contour ridging and ploughing in the catchment reduces both run off and erosion, which is the same measure that appears in water harvesting as a way of holding water in the field.
Leave a band uncultivated. Keep a strip of uncultivated land close to the reservoir and to any watercourse feeding it. It is the cheapest sediment trap there is and it needs no maintenance.
Fix the gullies. Gullies and other high run off areas must be reclaimed or at least stabilised. A single active gully in the catchment can silt a farm reservoir faster than the rest of the land put together.
Protect the waterways. Conserve the natural drainage lines rather than cultivating through them, so water arrives slowed and filtered instead of loaded.

There is a second reason to take this seriously. Silt costs you volume, and it costs you filtration too. Water carrying fine sediment blocks drip emitters, and the remedy is a settling stage before the filter, which is one more thing a reservoir asks of you. The filtration chain itself is covered on drip irrigation explained.

The Safety of an Open Water Body on a Farm

This section exists because a farm reservoir is a drowning hazard placed on land where children live, and that deserves stating plainly rather than in a footnote.

The World Health Organization puts annual drowning deaths worldwide at around 300,000, with children under five accounting for nearly a quarter of them. Drowning is the fourth leading cause of death for children aged one to four and the third for children aged five to fourteen. Ninety two per cent of drowning deaths occur in low and middle income countries, where rates run more than three times higher than in high income countries, and WHO names the daily use of ponds, rivers, lakes and open wells as part of why that exposure is higher. It also states the mechanism that matters most on a farm: the risk to young children rises when they interact with water outside active adult supervision.

WHO's prevention list is short and physical. Covering wells, doorway barriers, playpens, fencing and otherwise controlling access to water hazards greatly reduces exposure and risk. Teaching school age children basic swimming and water safety skills works too, and supervised childcare for pre school children reduces drowning risk and carries other health benefits with it.

What to build into a farm reservoir at construction, when it is cheap, rather than after an incident.
Fence it, and fence it properly. FAO treats fencing as necessary to keep livestock, people and vehicles off the embankment, the spillway and the outfall, and says the fence should be provided at the time of construction and kept in order, with every post checked at the annual inspection. A fence installed later, or left broken, is a fence that is not there.
Put up signs. FAO lists signboards and safety advice notices among the items to install during construction. They cost little and they mark the hazard for people who do not live on your farm.
Give the water to the animals somewhere else. FAO says troughs are always recommended and that no livestock should be allowed to drink directly from the reservoir. That is a safety measure and a water quality one together, and it removes the trodden muddy edge that makes a bank dangerous to stand on.
Pipe drinking water away from the water body. The manual notes that providing drinking water downstream through a pipe with a simple sand filter and a standpipe under gravity pressure reduces the need for people to go to the reservoir at all. Removing the reason to go near the water beats warning people not to.
Think about the edge before you dig it. A steep sided bank in slippery clay is hard to climb out of. Discuss the bank profile and any means of getting out with whoever designs the excavation, along with the fencing line, at the design stage rather than after the machine has left.
Supervise, and say so out loud. The single measure WHO's evidence points to hardest for the youngest children is active adult supervision. On a working farm that means a rule everybody in the household knows, not a good intention.

Water Quality and Herd Access Around a Farm Reservoir

An open body of standing water on a farm is a habitat, and FAO's guidance on managing that is practical rather than alarmist. To reduce the incidence of schistosomiasis, malaria and other water borne diseases, it advises keeping grass cover around the reservoir and in flowing channels to a minimum with regular cutting, raising and lowering reservoir levels rather than holding them steady, and removing standing water in and around the structure. Fencing to prevent access does part of the work.

Livestock access is the other half. Beyond the drinking prohibition, FAO warns against animals damaging the surroundings by overgrazing the catchment, tracking in the immediate surrounds of the reservoir and wallowing in the water itself. Each of those does two things at once: it adds sediment and it destroys the vegetative cover that was holding sediment back. A herd with a trough and a fence costs you a pipe and some wire and saves you volume every season.

For irrigation water quality, the practical consequences are silt and algae rather than chemistry. Both are handled by a settling stage and a filter ahead of any dripline, and both get worse in a shallow warm reservoir than in a deep one, which is one more argument for the shape conclusion above.

Permits, Excavation and Getting a Farm Reservoir Built

Three practical matters before you commit.

The permit position is genuinely important and it is not something to take from a website, this one included. Impounding or diverting surface water and taking water with a motorised pump both sit inside Uganda's permit system, and construction permits apply separately to works that impound, dam, divert or convey surface water. Categories, thresholds and fees are set by the regulator and they change, so confirm yours with the Ministry of Water and Environment or your district water office before the machine arrives, not after.

On the excavation itself, compaction is the line item to protect when the budget tightens. FAO's advice is to pay more for the equipment that does it properly, because that cost is recovered in a better and safer structure, and a poorly compacted embankment is the one failure on this page that can hurt somebody downstream. Layer by layer construction also allows staged building across two dry seasons, with one condition the manual insists on: whatever height the wall reaches in the first season, a spillway must be in place, temporary or permanent, to take flood flows safely away from the unfinished works.

And on the spillway itself, this page deliberately gives no dimensions. Spillway sizing depends on the catchment area and the design flood, it is where small dams fail catastrophically, and a number from an article is worse than no number. That is a calculation to get from somebody who will put their name to it.

Farm Reservoir Construction: Questions Farmers Ask

What does a farm reservoir cost in Uganda? It is quoted as an earth moving job, so the drivers are cubic metres moved, the machine and operator rate per hour or per day, how far that machine has to travel to you, and the ground it has to cut. Rock or hard laterite changes the figure completely. Get quotes on a stated volume and a stated depth from more than one contractor, and make sure each quote says separately what it includes for compaction, for the embankment, for the spillway and for fencing, because those four are where cheap quotes are cheap. Where the cost sits relative to the rest of an irrigation system is set out on irrigation system cost per acre.

How big should my reservoir be? Multiply your irrigated area by your daily application depth by the number of dry days you must cover, then add for evaporation and seepage. For one acre of vegetables over a ninety day dry season that lands near 1,500 cubic metres before losses. Use the irrigation water requirement calculation for the daily figure rather than the bracket on this page, because your crop and district move it.

Is a reservoir cheaper than a borehole? Often, and it is worth costing first for exactly that reason, but they are not substitutes. A reservoir depends on run off or on a source that runs long enough to fill it, and it loses water every day it sits. A borehole delivers on demand and does not evaporate, at a much larger and less reversible outlay with an uncertain yield until it is drilled. Compare them on your own site rather than in general, using boreholes for agricultural irrigation for the drilling side.

Will a plastic liner solve my seepage? Not on its own, and in the tropics it brings its own problems. FAO records liners attracting termites and rodents, being burrowed into by animals, and failing to cope with embankment settlement after construction. Compaction first, a cutoff trench second, a liner third, and never a liner instead of the first two.

Why is my reservoir empty by the end of the dry season when I calculated enough water? Almost always because evaporation and seepage were left out of the sum. A shallow broad pond can lose a quarter of its contents to the air over ninety days before anybody irrigates anything, and seepage is on top of that. Dig deeper and narrower next time, and recalculate with losses included.

Can I stock fish in an irrigation reservoir? It is done, and the water body is capable of it, but the two uses pull against each other: irrigation draws the level down at exactly the season fish need depth, and fish farming wants water quality management that irrigation does not. Treat it as a separate enterprise decision rather than a free extra.

How often will it need desilting? That depends entirely on the catchment, and the more useful answer is that FAO considers excavating a severely silted reservoir uneconomic, so the plan should be to reduce sediment at source and, if capacity is lost anyway, to raise the wall rather than dig the silt out. Inspect the depth at the same point every year so you know your own rate rather than guessing.

Do I need an engineer? For anything with an embankment holding water above the surrounding ground, yes, for the spillway and the wall at minimum. For a simple excavated pit with no retaining wall, the soil tests, the volume and the safety measures on this page get you most of the way, and a contractor who has built several nearby is worth more than a brochure.

Auger the site, roll the ball, fill the holes and watch the levels fall. Those four tests cost nothing and they answer the only question that matters before money is committed. When the soil says yes, write down your volume, your intended depth and your fencing line, and take that to two or three excavation contractors so the quotes can be compared on the same job. For the pump and pipe that come afterwards, suppliers sit under where to buy irrigation equipment, while the irrigation and greenhouses guide sets out what the reservoir will end up feeding. For a pump that does not need fuel hauled to a remote water body, see solar water pumps for farms, and for filling the reservoir from roofs and run off, rainwater harvesting for farms.

More in Irrigation and Greenhouses